PROJECT DETAILS

Project Name – New Plasterboard Line, Bristol

Client – Etex Building Performance Products

Project Value – £45.0M Construction / £65.0M Plant & Equipment

Date Completed – 2024

Services Provided – Quantity Surveying / Project Management / Principal Designer / Risk Management

Architect/Engineer – Maber Architects

Form of Contract – NEC3 Option A

PROJECT DESCRIPTION

Development of a completely new line of plasterboard manufacturing adjacent to the existing plasterboard manufacturing plant. The project comprises some 40,000 m2 of factory space including new line, materials input and storage and final product distribution. The original site is highly contaminated and requires extensive remediation.